Most of the I-55 construction news in Jefferson County covers MoDOT's $246 million rebuild between Route Z in Pevely and U.S. 67 south of Festus. None of that project's interchange work is in Imperial. Someone who lives in Imperial and works in St. Louis County or downtown drives north toward the Meramec River. That trip runs through a smaller project on the I-55 bridges between Meramec Bottom Road and Route 141 in Arnold, and that project lasts longer.
The two projects run on different schedules. MoDOT expects the Pevely-to-Festus work to wrap up in spring 2027. The same spring, the Meramec bridge work moves onto the northbound span. If you're comparing Imperial with Arnold, Oakville, or towns farther down I-55 and expect to close sometime in 2027, these dates belong in your planning.
The $246 Million Project Isn't on Your Route North
MoDOT's project is called "Interstate 55 Corridor Upgrades in Jefferson County." It adds a third lane in each direction along about eight miles from Route Z to U.S. 67. It also rebuilds the interchanges at Route Z, McNutt Street in Herculaneum and U.S. 67, with minor work at Route A. The project includes 27 bridges: 14 replacements, eight rehabilitations, four superstructure replacements and a new Route CC bridge over U.S. 67. KCI is the design-build contractor and was selected in July 2023.
The Jefferson County Leader reported that the original finish date was December 2026. MoDOT's project page now lists Spring 2027. Project director Justin Wolf gave a more specific goal to the Leader: "our goal is to have the entire project, including the new northbound bridges over Union Pacific railroad, Route Z and BNSF railroad, open to traffic before Memorial Day weekend."
None of these interchanges are in Imperial. Route M, Exit 185, shows up in MoDOT's project notices only as a signed detour during overnight I-55 closures between Route M and Route Z. Imperial Main Street, Old Antonia Road and Route 141 are outside the project's interchange work. For an Imperial household, this project affects trips to Pevely, Herculaneum, Festus and U.S. 67, and those trips should get easier once it's done.
The weeks before Thanksgiving are the busy final stretch. In October, MoDOT told the Leader it planned to open the southbound Route Z ramps and move southbound traffic onto the new alignment in late November. It also planned to open the new Route CC interchange at U.S. 67 before Thanksgiving. MoDOT's weekly report for November 12 through 18 still listed the southbound on- and off-ramps at Route Z as closed. MoDOT area liaison Jordan Dalaviras told the Leader the third southbound lane should open "before the end of the calendar year," together with the U.S. 67 interchange, because "more than half of the southbound I-55 traffic goes to southbound 67, especially at afternoon rush hour." Next comes the northbound side at Pevely. MoDOT's summer newsletter puts northbound reconstruction in the Route Z area starting in December 2026.
The Bridge at Arnold Is on Your Route North
Driving north from Imperial, you cross the Meramec River on a pair of bridges built in 1964. MoDOT replaced the deck and widened them to five lanes each way in 1993. The current project covers deck repairs, resurfacing, expansion joints, bearings and some structural steel. MoDOT estimated construction at $17.8 million. The Leader reported that Kozeny Wagner Construction submitted the lowest of four bids and will be paid $16.5 million.
MoDOT says at least four lanes will stay open in each direction during peak travel times for the whole project. When work began in March 2026, northbound I-55 dropped from five lanes to four. The Leader reported the lanes narrowed to 11 feet.
Southbound repairs came first, and MoDOT expects every southbound lane on that bridge to reopen in December. The northbound bridge, the one you use to get to work, is next. MoDOT says that work begins in March 2027. In those last two phases, as described by the Leader, three northbound lanes stay on the northbound bridge and two northbound lanes cross over to run on the southbound bridge. Southbound drivers keep four lanes. MoDOT's project page gives summer 2028 for completion. The Leader's report said spring 2028.
So in spring 2027, Imperial's two directions get opposite news. MoDOT expects the Pevely-to-Festus work to be finished around Memorial Day. The trip north will have only just entered its northbound phase, with lanes split across two bridges for a year or more after that.
Route 141 and Errands in Arnold
The bridge work zone ends at Route 141, so the Arnold interchange is part of it. While the bridges are under repair, MoDOT closes the northbound Route 141 left-turn lane to the on-ramp, and southbound Route 141 drivers yield before entering the ramp. During the southbound traffic split that began in August, Jefferson County said drivers could reach the Route 141/Arnold exit only from the right two southbound lanes.
Our recent post on what's opening in Arnold's storefronts covers some of the shops and restaurants near that interchange, and the Route 141 ramp changes apply to any errand run that uses it.
North of the River, the Next Project Starts in 2027
The bridge isn't the last work zone between Imperial and the city. MoDOT's 2026-27 construction guide schedules I-270 bridge rehabilitation between I-44 and I-55 for 2027 through 2028. That includes the bridge carrying the ramp to northbound I-55 and the Forder Road bridge, with at least three lanes open each way on I-270. If your commute uses I-270, the two projects overlap in 2027, so a crossover lane pattern at the Meramec and bridge work on I-270 could be on the same daily drive.
The 2027 work on Route 141 itself is a signal upgrade at Parkway South Middle School and Springdale Lane, not interchange reconstruction. East-West Gateway's FY2027-2030 Transportation Improvement Program lists scoping for overpass and ramp rehabilitation on I-44, I-55 and I-70 inside St. Louis City, without a funded construction project on that part of I-55.
The Commute Calendar for a 2027 Move
These are the scheduled dates as of mid-November 2026, with MoDOT's November 12 through 18 report as the latest status. All of them are targets.
| When | Where | What's scheduled |
|---|---|---|
| Late November 2026 | Route Z, Pevely | Southbound ramps open, southbound traffic moves to the new alignment |
| December 2026 | Meramec River bridge | All southbound lanes reopen |
| December 2026 | Route Z, Pevely | Northbound reconstruction begins |
| Before end of 2026 | McNutt to U.S. 67 | Third southbound lane opens with the U.S. 67/Route CC interchange |
| March 2027 | Meramec River bridge | Northbound bridge work begins |
| 2027 | I-270, I-44 to I-55 | Bridge rehabilitation begins, running through 2028 |
| Before Memorial Day 2027 | Route Z to U.S. 67 | Full corridor project open to traffic |
| Spring to summer 2028 | Meramec River bridge | Construction complete |
If you close in Imperial in spring 2027 and work north of the river, you'll probably move in around the time the northbound Meramec phase starts. Someone moving to Festus or the U.S. 67 corridor that same spring will probably arrive after the Pevely-to-Festus widening is finished. In Oakville or Mehlville, north of the Meramec, the bridge is part of the drive only on trips into Jefferson County. These schedules are temporary and the house is long-term, but the first year of a commute is part of living in a new home.
Transit Won't Get You Around It
Transit isn't a practical way around the bridge for an Imperial commuter. Metro's Route 9 Oakville runs between Telegraph & Baumgartner and the Shrewsbury-Lansdowne Transit Center on its schedule effective September 14 through November 29, 2026, and it doesn't serve Imperial or Arnold. OATS Transit's Jefferson County service has weekday Arnold shopping and medical trips from 10 a.m. to 1 p.m., Arnold-to-St. Louis medical trips on the third Tuesday of each month, and countywide service weekdays from 7 a.m. to 7 p.m. Its published schedule has no rush-hour commuter run downtown. If you're commuting from Imperial, plan on driving I-55.
Frequently Asked Questions
Does the I-55 widening add lanes in Imperial? No. The third lane each way runs from Route Z in Pevely to U.S. 67, and Imperial's interchanges are outside the project's scope.
Will I-55 at the Meramec River ever drop below four lanes during rush hour? MoDOT's stated commitment is at least four lanes open in each direction during peak travel times for the whole project. Its notices describe overnight closures from 7 p.m. to 5 a.m. for restriping and barrier work.
Where can I check the current lane closures before a showing or a commute test drive? MoDOT posts a weekly construction report and keeps project pages for the I-55 corridor upgrades and the Meramec River bridge rehabilitation.
If you're weighing Imperial against Arnold or Oakville and plan to move in 2027, The Becky O'neill Real Estate Team can talk through how your closing date lines up with the I-55 construction schedule. If you're an Imperial owner wondering how a buyer's commute questions affect your sale timing, start with a home value consultation.